???? 據2月22日offshore energy消息:日本石油勘探公司(JAPEX)表示,將繼續從Soma液化天然氣終端向鄰近的福島核電站供應再氣化天然氣。
????需要提醒的是,由于2月13日日本發生7.3級地震,這兩處設施都已關閉。
????隨著Soma液化天然氣終端天然氣供應的恢復,福島天然氣電力公司旗下的福島電廠也恢復了運營。
????2月16日,該公司初步恢復了對天然氣管道網絡和液化天然氣卡車的再氣化液化天然氣供應。
????在確認終端有關設施安全后,發電廠的液化天然氣再氣化供應已于二月十九日恢復。
????由于地震發生后發電設施自動關閉,FGP進行了檢查,沒有發現影響電廠運行的設施損壞。電廠1號和2號機組已于2月19日恢復運行。
????Soma液化天然氣設施的產能為700萬噸/年,而福島天然氣發電廠的產能為118萬千瓦。
????馮娟 摘譯自 offshore energy
????原文如下:
????JAPEX resumes full operation at Soma LNG
????Japan Petroleum Exploration (JAPEX) said it has continued the supply of regasified natural gas from Soma LNG terminal to the adjacent Fukushima power plant.
????To remind, both facilities have been shut down due to a 7.3 magnitude earthquake that hit Japan on February 13.
????With the resumption of natural gas supply from the Soma LNG terminal, Fukushima power plant, owned by Fukushima Gas Power, also resumed operation.
????JAPEX noted that operations have sequentially been resuming as safety was confirmed through inspections, restoration measures and trial runs.
????The company initially resumed supply of regasified LNG to the gas pipeline network and LNG trucks on February 16.
????With the confirmation of the safety on related facilities at the terminal, the supply of LNG regasified gas for power generation to the power plant resumed on February 19.
????As a result of checks and inspections conducted by FGP after the automatic shutdown of the power generation facilities following the earthquake, there was no damage to the facilities that would interfere with the power plant’s operation.
????With the resumption of fuel supply from the Soma LNG terminal, the power plant resumed operation on February 19 as well, for both Unit No.1 and No.2.
????To remind, the Soma LNG facility has the capacity to handle 7 mtpa of LN, while the Fukushima natural gas power plant has a production capacity of 1.18 million KW.